More than one nexttask in gantt graph
Posted: Tue Mar 09, 2004 2:39 pm
by 6922300
Hello all,
I need put more than one nexttask in gantt graph to use him how a Project.
It is possible?
Thanks for help,
Morpheu
Posted: Wed Mar 10, 2004 9:49 am
by Pep
Hi Morpheu,
each Gantt bar can be connected only to one "next task". If you need more than one connection per Gantt bar, then the only way to do it is to add more GanttSeries, populate it with the same Start, End and Y values and then use each series for different connection (different NextTask for each series).
Posted: Thu Mar 11, 2004 1:57 pm
by 6922300
Hi,
Thanks for help, but I can make one question?
Exists plan for improve this feature?
To create more series is not the best solution, mainly when I have to reproduce a project accompaniment that have for each task: planned, accomplished, new forecast.
Pep wrote:Hi Morpheu,
each Gantt bar can be connected only to one "next task". If you need more than one connection per Gantt bar, then the only way to do it is to add more GanttSeries, populate it with the same Start, End and Y values and then use each series for different connection (different NextTask for each series).
Posted: Tue Mar 16, 2004 8:49 am
by Pep
Hi Morpheu,
I've add this feature on our wish list to be considered to inclusion for the next releases of TeeChart.